Varanasi airport expansion to run runway over 2.89 km underpass, terminal nears completion

A 2.89-km underpass is being built on NH-31 so Lal Bahadur Shastri International Airport’s extended runway can pass above it; the underpass and a new terminal are due for completion next year.

By Desh in Last 24Hr Desk2 min read

The National Highways Authority of India is constructing a 2.89-kilometre underpass on NH-31 at Varanasi to allow the expanded runway of Lal Bahadur Shastri International Airport to run above the highway, a configuration that will be the first of its kind in India. The underpass project is estimated to cost Rs 649.44 crore and forms part of a larger airport expansion valued at about Rs 2,870 crore.

Work on the underpass had reached nearly 60% completion by November 2026 and is targeted for completion by March 2027. The new terminal building has reached substantial completion—reported between 71% and about 89% in different updates—and is expected to be finished between December 31, 2026 and July 2027 in the various project timelines provided.

Why the unusual design was chosen

The airport’s expansion had been constrained for almost two decades because a railway line bordered the eastern side and the Varanasi–Lucknow national highway ran along the west, so extending the runway westward required preserving the highway’s alignment. The Airports Authority of India first proposed extending the roughly 2,750-metre runway to 4,075 metres in its 2004 masterplan and revived land-identification work in 2017.

In 2018 the AAI approved extending the runway over the highway while constructing an underpass beneath it. Land acquisition and administrative and technical matters delayed progress until renewed urgency following flight disruptions due to dense fog in January 2023 prompted directions to accelerate the work.

"It will be India's first highway to pass under the runway of an airport."

The Union Cabinet cleared the broader airport expansion in June 2024 and Prime Minister Narendra Modi laid the foundation stone for the airport project on October 20, 2024, and later for the underpass. District authorities sought land acquisition funding in July 2023 to acquire about 593.77 acres across seven villages for the expansion.

New terminal details and capacity

The new terminal, being built over about 75,000 square metres at a cost reported as around Rs 900 crore, will have eight aerobridges, 72 check-in counters, eight conveyor belts and 14 security counters, and aims to handle more than 6 million passengers a year. Work on a multi-level car park is nearly finished and interior finishing, including painting and a dome feature, was reported to be in final stages.

Officials set targets for the terminal to be completed by December 31, 2026, with a possibility of an inauguration by the Prime Minister in early January 2027, and other reports place a July 2027 completion date for some airport elements.